RD45 - Milestones for 1998
The milestones for the second half of 1998 and 1999 were set at the
LCB Meeting in April 1998
and are listed below.
- Provide, together with the IT/PDP group, production data management services based on Objectivity/DB
and HPSS with sufficient capacity to solve the requirements of ATLAS and CMS test beam and simulation
needs, COMPASS and NA45 tests for their '99 data taking runs.
- Develop and provide appropriate database administration tools, (meta-)data browsers and data import/export
facilities, as required for (1).
- Develop and provide production versions of the HepOODBMS class libraries, including reference and
end-user guides.
- Continue R&D, based on input and use cases from the LHC collaborations to produce results in time
for the next versions of the collaborations' Computing Technical Proposals (end 1999).
Jamie.Shiers@cern.ch